Question: 1 / 50

Are the following statements regarding the Starting Up a Project process true or false? 1. How the project will achieve the required quality will be established 2. How the corporate (or programme's) project management method will be tailored to suit the project will be defined

Both are true

Both are false

The Starting Up a Project process within the PRINCE2 framework is crucial for setting the stage for successful project execution. In this process, two key activities are involved: establishing the project’s viability and ensuring that a robust foundation is laid for project initiation. The first statement addresses how the project will achieve the required quality. While quality expectations are considered at this stage, the detailed planning and establishment of how quality will be achieved typically occur later in the process. The focus during the Starting Up a Project process is more on defining the project’s objectives, scope, and ensuring that all necessary prerequisites for successful project initiation are in place, rather than on the intricacies of the quality management aspects. The second statement emphasizes the tailoring of the corporate or programme project management method to suit the project. Tailoring is indeed a part of project management; however, the implementation of how the method will be tailored is often addressed more explicitly during the Initiating a Project process rather than the initial setup. Here, the aim is to decide whether or not to proceed with the project based on initial assessments, rather than detailing the tailoring process. Since both statements address aspects that are not a core focus of the Starting Up a Project process, they are considered false. Hence, identifying

Only statement 1 is true

Only statement 2 is true

Next

Report this question